Data centers and mission critical

Campus builds with more MEP than structure, schedules set by power delivery, and owners who build the same building many times.

How the teams are shaped

On a large data center campus the mechanical and electrical scope carries much of the contract value, so the MEP Manager or MEP Director often has more influence over the job than a traditional Senior PM. Hire them early. They should be in the room for trade buyout.

Commissioning starts on day one. The Commissioning Manager’s plan shapes the sequence of the whole job, and a team that treats it as closeout will be rebuilding switchgear rooms in the last quarter.

Repeat owners expect repeat teams. A contractor that does well on building one is often asked to do buildings two to six, and the client will want the same Project Executive and General Superintendent. Plan for that when you hire them.

Markets

  • Phoenix
  • Dallas to Fort Worth
  • Atlanta
  • Northern Virginia, which sets the pay everyone else reacts to
  • Dublin, occasionally

Seats we’re asked for most

  • Project Executive
  • MEP Manager or MEP Director
  • Commissioning Manager
  • General Superintendent
  • Safety Director
  • Quality Manager

A delivery team for a multi-building campus

SeatScopeWhen
Project ExecutiveThe owner relationship across the campusFirst
MEP DirectorElectrical and mechanical scope, long lead equipment, vendor coordinationFirst or second
General SuperintendentField leadership across buildingsBefore mobilization
Senior Project ManagerOne per building or phaseStaggered with the phases
Commissioning ManagerCommissioning plan and integrated systems testingPreconstruction
Safety DirectorSite based on large campusesBefore mobilization
Quality ManagerInspections and owner quality requirementsBefore the first building goes vertical

Where it goes wrong

Hiring a strong commercial building Project Executive who has never dealt with a utility on a power delivery schedule. It’s a different job. The schedule is driven by things outside the fence, and the PX has to manage those relationships as hard as the ones inside it.

Underpaying the MEP lead. They know exactly what they’re worth in this market, and so does every competitor. If you lose one mid-campus, replacing them is slow and expensive.

Staffing a campus.

Tell us the owner type, the number of buildings and where it is. We’ll start with the MEP lead.